Bangalore metro / Namma Metro train travel from Baiyyappanahalli to M.G. Road it is opened sterday 20 October 2011. Here you will get the Bangalore metro map, Bangalore Metro Route Map, Bangalore Metro Map Gallery. Construction Phase I
[edit] Future expansion The BMRC plans to build a Metro rail to the Bengaluru International Airport, probably starting at Cubbon Road.[12]
Implementation of the elevated parts of Phase I has been divided into four "reaches". Reach I of the proejct will cover The Byappanahalli-M.G. Road link with six stations and travel time of around 14 minutes.
The expected deadlines for Phase I are as follows:
Reach
|
Terminals
|
Opening/Expected completion date
| |
Reach-1 (east) | Byappanahalli | M.G. Road | 20 October 2011(opened)[4] |
Reach-2 (west) | Mysore Road | Magadi Road | August 2012[10] |
Reach-3 (north) | Swastik | Yeswanthpur | November 2012[10] |
Reach-3A (north) | Yeswanthpur | Peenya Depot | December 2012 |
Reach-3B (north) | Peenya Village Station | Hessarghatta Cross Station | August 2013 |
Reach-4 (south) | K.R. Road | R.V. Road | December 2013 |
Reach-4A (south) | R.V.Road | Puttenahalli | August 2013 |
The elevated lines will now become functional in the following stages:
- The Eastern line (Reach -1) by 20 October 2011
- The Northern line (Reach 3,3A & 3B) by the end of 2012
- The Western (Reach 2) and Southern (Reach 4) lines by March–June 2013.
Phase II
Covering a span of 70 km, Phase II is an extension of all the four Reaches (Reach 1 to 4) and is expected to reduce road traffic by 35% . Additionally Phase II will also have two independent lines – one from Jayanagar to Electronic City and the second from Nagavara to IIM-B, a total of 21 km of which around 15 km will be underground route. The estimated project cost for Phase II is around 25,000 crore (US$5.58 billion)
Route
|
Terminals
|
Length
|
Stations
|
■ Line 1 | Jayanagar – Electronic City | 20 km | 19 |
■ Line 1 | Puttenahalli – Anjanapura | 6.79 km | 6 |
■ Line 2 | Mysore Road – Kengeri | 7.70 km | 8 |
■ Line 2 | Byappanahalli – Whitefield[12] | 18 km | 17 |
■ Line 3 | IIM-B – Nagavara | 24 km | 20 |